arrow_backBack to projects near Anglesey
Reference: 10C118A/RE·repd:2353
Solar/Wales

Bryn yr Odyn Solar Farm

Applicant / operator: New Forest Energy Ltd. Record drawn from the DESNZ Renewable Energy Planning Database extract. Status and capacity are as published in that source.

Current Statusoperational
Capacity15MW
Planning authorityIsle of Anglesey
Location confidencecoordinate

Progress track

  1. Passed
    proposed
  2. Passed
    in planning
  3. Passed
    approved
  4. Passed
    under construction
  5. Now
    operational

What it means

This is a public planning-database record, not a live operational feed from the site. Capacity is installed or proposed electrical capacity as published (MWelec). Coordinates are converted from British National Grid where available; confidence is labelled.

Technology
Solar
Developer / applicant
New Forest Energy Ltd
Coordinates
53.2333, -4.4047
Extract
2026-09-16

Location

1 pin

  • Operational
  • Construction
  • Approved
  • In planning
  • Proposed

Click pin or list card — popup stays on the map

Further reading

Links to dig deeper. We only store the REPD fields above today — these are curated search/official links, not scraped pages. Richer application URLs will land here when we add them to the warehouse.

Source: DESNZ REPD (OGL v3.0) · Source updated 2015-04-16 · We checked 2026-09-16T15:45:16.169092000Z · As of 2026-09-16